Annual Report 2012

FACILITIES & CONSTRUCTION

NEW PROJECTS
ADVANCE TOWARDS
COMPLETION

SEHA IS LEADING OR INITIATING SEVERAL MAJOR CONSTRUCTION PROJECTS THAT ARE BEING IMPLEMENTED IN PHASES AND WILL BE COMPLETED OVER THE NEXT FIVE TO 10 YEARS. THIS HUGE INFRASTRUCTURE EFFORT WILL TRANSFORM THE SEHA HEALTHSYSTEM, DEFINING ITS ROLE AS THE LEADING HEALTHCARE PROVIDER AND INFLUENCING ITS STANDING AND PERCEPTION IN THE EMIRATE OF ABU DHABI, THE UAE, AND BEYOND.

THE CURRENT STATUS OF THE VARIOUS PROJECTS IS:

Mafraq Hospital

• Concrete structure completed and topping out ceremony held. Work involved laying about 250,000 cubic m. of concrete and 31,000 tons of reinforcement steel bars.
• Mock-up building is completed after thorough review by all parties, including functional considerations, aesthetics, durability of materials, and workmanship.
• Biomedical Equipment and Hospital Furniture package completed. Contractors underwent prequalification and tenders are being evaluated.

Al Ain Hospital

• Awaiting Executive Council approval for the main works package.

Sheikh Khalifa Medical City

• Tender document completed.
• Prequalification of main works contractors completed.
• Traffic impact study and circulation plan completed and approved.

Al Sila & Ghiathy Hospital

• Main works contract awarded.
• Construction under way.

Mafraq Dialysis Center

• Completed and handed over to the operator.

Tawam Dialysis

• Executive Council budget approval obtained.
• Main works contract awarded.
• Mobilization and excavation works under way.

SKMC Dialysis

• Tenders should be received by mid-January, 2013.

Long Term Custodian Care Center for Zayed Higher Organization

• Completed and handed over to the operator.

New England Center for Children

• Completed and in process of handing over to the operator.

SKMC Emergency Department

• Phase 1 completed and Phase 2 in hand-over process.

Al Wagan Hospital

• Tender evaluation under way.

New Rehabilitation Center

• Tender evaluation completed.

SKMC Royal VIP

• Phase 1 completed. Phases 2 and 3 due for hand-over by end-January, 2013.

Disease Prevention Screening Center, Abu Dhabi

• Tender document completed and issued to bidders.

Al Rahba Emergency Department

• Technical & financial evaluation report is completed.
• Recommendation from the evaluation committee sent to SEHA procurement for approval.

Sir Bani Yas Temporary Clinic

• Final design completed.
• Obtained project approval from HA-AD & Executive Council.
• Project cost quotation received and awaiting SEHA management approval.

Ambulatory Clinics Phase I (nine clinics)

• Construction nearly 85% completed.

Clinics Phase 2 (four clinics)

• Final design completed.
• Tender evaluation 90% completed.

OR and Pediatric SKMC Renovation

• Project completed and handed over.